Wise Street, Leamington Spa

Overview:

The Wise Street site, operated by our customer, plays a key role in the power distribution network, ensuring the supply of electricity across key areas.

This case study focuses on the installation of the second transformer (T2) at the site, following the successful installation of the first transformer (T1) back in June 2024. This installation was critical in enhancing the site’s capacity and reinforcing the reliability of the electricity supply to the surrounding area.

The transformer installed at Wise Street was a 20/40MVA, 33/11.5kV, Dyn11 power transformer. The installation of this second unit was part of our customers ongoing upgrade to meet the growing demand for energy and increase the system’s supply reliability.

Project Photos

Our Process:

The transformer was carefully delivered to the site by Colletts, a trusted haulier known for their experience with large scale transportation and handling of heavy equipment. The transportation process, including the coordination of traffic and precise timing, was critical to ensuring the transformer arrived safely without any delays.

Our site engineers, led by Tom Allan as the Lead Field Engineer, oversaw the unloading and positioning of the transformer. The team, including Karl Blackburn, Adam Davison, and Sam Baker (who had also been part of the T1 installation), followed a detailed step by step plan to ensure the transformer was positioned precisely for operation.

The team worked efficiently through the installation of all electrical connections, mechanical fittings, and safety checks. Given the complex nature of the installation, each member of the team played a crucial role in completing the task smoothly, maintaining a high level of safety throughout the process.

  • Coordination with Haulier: The successful transportation of a transformer of this size and weight requires careful planning. Colletts ensured that the heavy load was transported safely, with all required permits and equipment for the task. The engineers maintained close communication with the haulier to address any logistical issues that could arise during the process.
  • Site Preparation: The installation of such a large transformer requires careful site preparation to accommodate the equipment. Site engineers worked alongside our customer representatives to ensure that the foundation, power lines, and connections were in place for the installation of the new transformer.
  • Safety Protocols: As with all transformer installations, safety was a top priority. The engineers adhered to strict safety standards and protocols, ensuring that all work was done with the highest levels of precision. The team conducted regular safety briefings, and risk assessments were performed throughout the installation process.

Outcome

The installation of the transformer (T2) at the Wise Street site was completed on schedule. The successful commissioning of this transformer enhances the capacity of our customers’ distribution network, providing increased reliability and security of supply to the surrounding area. The combined efforts of the Colletts hauliers, the site engineers, and our customer’s staff ensured that this installation met all expectations.

Let's work
together

Looking for an expert team to work on your next transformer project? Whether you need custom solutions, technical advice, or a reliable partner, we’re here to help. Tell us about your project by filling out the contact form, and our team will be in touch to discuss how we can power your success!

Partha Subramanian

Technical & Business Development Director

Partha joined Winder Power as our Technical & Business Development Director. With a first class bachelor’s degree in engineering and a successful career spanning over two decades, Partha brings a wealth of experience from industry leaders. His expertise in developing 132kV product lines and overseeing projects from start to finish will be invaluable to our team.

Partha’s strategic approach to planning, vendor management, and innovative solutions will drive business growth and ensure the timely delivery of high-quality power transformer projects. He will play a key role in identifying new opportunities, expanding our customer base, and developing innovative solutions to meet evolving market needs.