Installation & commissioning of 1 x 5MVA, 13/11kV transformer & 1 x 13kV earthing transformer
Client:
Undisclosed
Peckham, London

Scope of work

  • Design, manufacture and testing of 1 x 1 x 5MVA 13/11kV transformer & 1 x 13kV earthing transformer.

Full in-house routine testing.

  • Delivery using a short trailer for site access then off-loading via hydraulic jacking and skating a one directional skid of 8m including pre-commissioning works as per the customers specification by our Substation Services installation & commissioning teams.